Milestones

  • Initial ideas to make Heaton safer, cleaner and greener

    October 2021

     

    -

     

    November 2021

    Plans shared with residents, businesses and other stakeholders and feedback gathered.
  • Plans refined

    December 2021

     

    -

     

    March 2022

    Stakeholder feedback analysed and considered.
  • Plans finalised

    May 2022

     

    -

     

    September 2022

    Legal orders drafted, phasing and work programming negotiated.
  • Implementation of package of measures

    24th October 2022

     

    -

     

    mid November 2022

    Stakeholders notified, implementation programmed and delivered.
  • Consultation on the measures

    24th October 2022

     

    -

     

    23rd April 2023

    6 month consultation period using on and offline channels.
  • South View West

    26th January 2023

     

    -

     

    31st July 2023

    Consultation on South View West trial closure